Архив

October, 12, 2012

Unit No 3 has successfully passed 72-hour integrated test.

September, 20, 2012

Steam turbine , unit No 3, has been connected to the electric grid for testing.

September, 17, 2012

Testing of the steam turbine , unit No 3, has been completed.

August, 29, 2012

The steam-water-oxygen cleaning of the boiler , unit No 3, has been completed.

August, 13, 2012

The overhaul of the steam turbine, unit No 2, has been completed.

August, 01, 2012

The first balancing launch of the steam turbine of unit No 2, being under repair, was carried out.