Zabaikalsky branch of “Termoelektro” operates at the construction of the 3rd unit of Kharanorskaya GRES (TPP), capacity 225 MW, to carry out erection of carcasses of the main building and heat mechanic equipment, boiler and equipment of machinery hall.

Construction period: 2008 – 2011

Customer: OAO “WGC-3” (“The third generation company of the wholesale electricity market”). General contractor: ZAO "Energoproekt".

Contacts: 674520, Russian Federation, Zabaykalsky Krai, Yasnogorsk town

Phone.: +7 495 645-23-10 (11), fax: +7 30253 6-29-60.

E-mail: zbtermo@mail.ru

Cherepetsky branch of “Termoelektro” operates at the construction of units № 8 & 9 of Cherepetskaya GRES (TPP), capacity 225 MW each, to carry out erection of carcasses of the main building, boilers and other technological equipment.

Construction period: 2010-2014

Customer: OAO “WGC-3” (“The third generation company of the wholesale electricity market”). General contractor: OAO “VO “TECHNOPROMEXPORT”.

Contacts: 301430, Russian Federation, Tula region, Suvorov town.

Phone/fax: +7 48763 2-80-93.

E-mail: te-suvorov@rambler.ru

Using the existing industrial base, Ivanovsky branch of “Termoelektro” produces pipelines for dust, gas & water (PGVP), auxiliary boiler equipment (KVO), various steel structures, low-pressure pipelines, as well as non-standard equipment: tanks, containers etc. up to 500 tons per month. The personnel of the branch performs erection and repair of energy objects in the region.

Contacts: 155902, Russian Federation, Ivanovskaya region, Shuya town.

Phone: +7 49351 4-85-92

E-mail: termoelektro@mail.ru

Voronezhsky branch of “Termoelektro” has been established to carry out construction & erection works at Novovoronezh nuclear power plant-2.

Contacts: 396070, Russian Federation, Voronezhskaya region, Novovoronezh town.

Beryozovsky branch of “Termoelektro” has been established to carry out construction & erection works at Beryozovskaya thermal power plant, unit № 3.

Construction period: 2011-2014

Customer: "E.ON - Russia" (former "WGC-4" - "The forth generation company of the wholesale electricity market”). General contractor: ZAO "Energoproekt".

Contacts: 662328, Russian Federation, Krasnoyarsky region, Sharypovsky district, prombaza "Energetikov", 5

Gusinoozyorsky branch of “Termoelektro” has been established to carry out erection of steam turbine at Beryozovskaya thermal power plant, unit № 4.

Construction period: 2011-2012

Customer: OAO “WGC-3” (“The third generation company of the wholesale electricity market”). General contractor: ZAO "Energia-Service".

Contacts: 671160, Russian Federation, Republic of Buryatiya, Gusinoozyorsk town.