Gusinoozyorskaya TPP, unit No ,, 210 MW, construction period: 2011 – 2012. Location: Republic of Buryatiya, town of Gusinoozyorsk. Customer: JSC “WGC-3”. General contractor: ZAO “Energiya-service”. “Termoelektro” LLC carries out erection of steam turbine.

 Test assembly of low-pressure cylinder

 

 Alignment of rotors

 

Installation of medium-pressure cylinder

 Installation of medium-pressure cylinder