Cherepetskaya GRES (TPP), units №№ 8 & 9, 225 MW each, construction period: 2010-2014. Customer: “WGC-3” (“The third generation company of the wholesale electricity market”). General contractor: “Technopromexport”. “Termoelectro” (Moscow) carries out erection of carcasses of the main building, heat mechanic equipment of units №№ 8 & 9, boilers and other technological equipment. Total weight of steel constructions and heat mechanical equipment – 22 167 tons.


General view of Cherepetskaya GRES (TPP) & the site 


Tower crane BK-1000 at the erection of the main building, units № 8 & 9


Erection of cranes of the machinery hall


Pre-assembly of steel constructions of the carcass of steam boiler Е-630-13,8-565/570 KT, unit № 8


Pre-assembly of steel constructions of the main building, units № 8 & 9 


Pre-assembly of heating surfaces of steam boiler


Erection of the main building of units № 8 & 9 (bunker-deaerator part) 


Erection of the main building of units № 8 & 9 (machinery hall) 


Pre-assembly of  the girders of bridging of machinery hall 


General view on the bunker-deaerator part & machinery hall

Erection of steel constructions & pipelines for air in the “G”-line

 


Erection of bridgings of blocks of girders of machinery hall

Erection of steel constructions of the temporary end of machinery hall

 

Erection of steel constructions of the boiler house & regenerative air heater

Erection of the carcass of the steam boiler

Erection of steel constructions of the pouring tower

Erection of steel constructions of the constant end of the boiler house, unit № 9

Pre-assembly of steel constructions of steam boiler, unit № 8

Erection of steel constructions of steam boiler, unit № 8

Demounting of the tower crane BK-1000

Covering of the heat contour, units № 8 & 9

Pre-assembly of steel constructions of heating surfaces & water economaizer of steam boiler, unit № 8